NCS was retained by a power generation facility to provide temporary treatment of cooling tower blowdown and lagoon water, increasing water reuse and minimizing brine discharge to the site’s evaporation pond in place of a conventional permanent capital project.
NCS designed, procured, and installed two temporary treatment systems working together. A high-pressure reverse osmosis system for the facility’s most concentrated stream, paired with a seawater-grade reverse osmosis system to handle the balance of the flow. Both systems were skid-mounted for rapid mobilization, with NCS supplying the associated pumps, piping, and electrical to support a fully turnkey installation.
Once online, the systems were run by NCS over several months, treating water well beyond the range conventional RO can typically handle and easing demand on the site’s evaporation pond. NCS provided ongoing performance monitoring throughout the deployment, then demobilized the equipment once it had served its purpose. Illustrating how a temporary, rental-based approach can resolve a time-sensitive water challenge without committing to permanent capital infrastructure.